Groups > Microsoft > Solomon > RE: AP period and check date




AP period and check date

AP period and check date
Mon, 31 Mar 2008 08:01:01 -070
Hello.  Will I be able to date a check run April 3rd if my Solomon AP module 
is still March?  

Post Reply
RE: AP period and check date
Mon, 31 Mar 2008 16:50:33 -070
Hi,
Yes.

You can change the check date to any date in an open 1099 year.  You can 
change the period to post in the Payment Selection screen or in the AP Check 
Update screen (the screen that pops up after the checks print).  Or you can 
accept the default date and the default period and allow a check dated Apr 3 
to post to March... the only consequence of that as far as I know is, when 
you reconcile cash that check will be in the GL for March but won't clear the 
bank until Apr.
-- 
Laura Barber


"SL_newbie" wrote:

> Hello.  Will I be able to date a check run April 3rd if my Solomon AP
module 
> is still March?  
> 
Post Reply
RE: AP period and check date
Tue, 1 Apr 2008 09:29:00 -0700
In addition to what Laura has posted there are some ramification of have a 
check date outside of your period to post if you are using Cash Manager.

Unless you have a specific business reason why you want to do this, I would 
recommend against it.  

Regards,
Christine Flora
CAPM, MCBMSP, MCTS, MCT
Project Manager / Microsoft Certified Trainer


"SL_newbie" wrote:

> Hello.  Will I be able to date a check run April 3rd if my Solomon AP
module 
> is still March?  
> 